On Oct. 23, 2025, the Department of Energy (DOE) sent the Federal Energy Regulatory Commission (FERC) a proposed Advanced Notice of Proposed Rulemaking (ANOPR) related to the interconnection of large loads and directed FERC to take final action no later than April 30, 2026. On Oct. 28, FERC established a new docket to consider DOE’s ANOPR and issued a “Notice Inviting Comments” (Docket No. RM26-4-000). In the notice, FERC set an initial comment date of Nov. 14 and a reply comment deadline of Nov. 28.
DOE Secretary Chris Wright acknowledged that historically, FERC “has not exerted jurisdiction over load interconnections,” but that it is his “view that the interconnection of large loads directly to the interstate transmission system to access the transmission system and the electricity transmitted over it falls squarely within the Commission’s jurisdiction.” The letter further noted that “[a]sserting [FERC] jurisdiction [over such interconnections] is in the public’s interest” to revitalize domestic manufacturing and drive American AI innovation, while doing so “efficiently, fairly, and expeditiously.” To that end, the DOE proposes 14 planning principles to apply to new large load interconnections on the transmission system, including the establishment of standardized procedures, agreements and requirements for large load (analogous to those for generator interconnection). The planning principles also cover cost responsibility and reliability issues.
While the ANOPR directs action by April 30, 2026, and acknowledges the possibility of additional transition periods, it also affirms that in the meantime, the proposal is “not intended in any way to discourage public utilities from making filings to address these and similar issues under [Federal Power Act (FPA)] Section 205.”
Read on to learn more about the DOE’s support for its action, the 14 planning principles and specific requests for comment.
Legal Authority for DOE’s Proposed Actions
1. Similar to generator interconnections, large load interconnections are a “critical component of open access transmission service” that require minimum terms and conditions to ensure nondiscriminatory service.
2. The interconnection of large loads to the transmission system is a “practice directly affecting [FERC]-jurisdictional wholesale electricity rates,” under FPA Section 205.
3. FERC jurisdiction over the interconnection process does not encroach on state authority over local distribution, generation siting or retail sales.
4. The proposal is consistent with the FPA’s core purpose. Under the FPA, FERC has exclusive jurisdiction over the transmission of electric energy in interstate commerce, including the rates, terms and conditions of transmission service, and all facilities for such transmission or sale of electric energy at wholesale in interstate commerce. Accordingly, any large load that seeks to interconnect to the transmission system does so to obtain transmission service and the appurtenant benefits of such.
Principles for Reform
The draft ANOPR establishes 14 principles for FERC to consider during a rulemaking process and poses topics for comment:
- Request for Comment: The ANOPR seeks comment on alternative thresholds, including whether a threshold is needed at all.
- Request for Comment: The DOE seeks comment on (a) the extent to which the existing study deposits, readiness requirements and withdrawal penalties (applicable to generation) can be adopted and (b) whether additional commitments or financial penalties would be appropriate.
5. Co-located facilities should be studied based on the amount of injection and/or withdrawal rights requested (i.e., a 500 MW load co-located with a 600 MW generating facility should be able to seek 0 MW of withdrawal rights and 100 MW of injection rights) to provide an “incentive” for co-location and efficient transmission build-out.
- Request for Comment: The DOE seeks comment on (a) whether other operational limitations should be considered; (b) the minimum technical requirements for such system protection facilities, whether a co-located interconnection customer should be subject to penalties for unauthorized injections or withdrawals, (c) how any such penalties should be designed and (d) how such penalties should be allocated to other transmission customers.
- Request for Comment: The DOE seeks comment on (a) whether this should be accomplished through a serial interconnection study process or by some other means, and (b) the appropriate deadlines for such an expedited study process, including whether such studies can be completed in 60 days.
- Request for Comment: The DOE seeks comment on whether (a) network upgrade costs should be offset through a crediting mechanism and; (b) if so, over how many years.
10. An existing generating facility that seeks to enter a partial suspension to serve a new load at the same location must go through a system support resource (SSR)/reliability must run (RMR) type study that considers system conditions, including forecasted load growth at least three years after the proposed suspension date. If such election is made, the partial suspension can only proceed after necessary network upgrades are placed into to service.
- Request for Comment: The DOE seeks comment on whether and how resource adequacy should be considered in the SSR/RMR type study.
13. There must be a plan to implement these proposed reforms.
- Request for Comment: The DOE seeks comment on appropriate transition plans, including the treatment of large load interconnections that are already being studied for interconnection.
14. Utilities serving large loads must meet all applicable North American Electric Reliability Corporation (NERC) reliability standards and open access transmission tariff provisions. NERC should evaluate whether new registration categories or new or modified reliability standards are required to ensure reliability of the bulk electric system.
The McGuireWoods FERC team continues to monitor any resulting proceeding.